3/8/2013 The roofer finished shingling today

3/8/2013

The roofer finished shingling today, and the cupola is on the peak.  The plumbers were in yesterday and roughed in about 80% of the house.  Can't do anymore until we get the basement floor poured.  With that in mind I started spreading Radon rock in the basement this afternoon.  Tough manual work, but gratifying to see something moving forward, no matter how slow.  We should be able to finish the rock and have most of the insulation down on the floor by the end of the weekend.  Then we'll be ready for HVAC to come in and lay pipe for the in-floor heat.

Basement plumbing roughed in and starting to spread Radon rock throughout.